(영문) 광주지방법원 순천지원 2014.04.02 2013고단572
뇌물수수
Text

Defendant

S Imprisonment with prison labor of April and fine of KRW 10,000,000, Defendant A with fine of KRW 3,000,000, Defendant K with fine of KRW 700,000.

Reasons

Punishment of the crime

Defendant

A is the representative director of (M) who performs the F Complex construction under a subcontract.

Defendant

K is the Deputy Director of the Management Agency of the I, who performed the removal works of Q area by sub-subcontracting them from M among the construction works of the F Complex.

U has been in charge of managing and supervising the construction of the F Complex from January 2009 to August 201, 201, and Defendant S was in charge of the management and supervision of the construction of the F Complex from January 2009 to August 201, and from January 201 to January 201, Defendant S was in charge of the management and supervision of the F Complex Construction from January 201 to January 201.

1. Defendant A

A. A. Around September 2009, the Defendant issued money and valuables to a third party for the purpose of accepting a bribe in relation to the public official’s duties by requesting G, who is the site manager of the F Complex Construction at W Office at W at W at W, to the effect that convenience is considered in the process of construction supervision in the process of construction supervision. The Defendant offered money and valuables to G, which is a public official in charge of supervision of the Public Corporation, for the purpose of accepting a bribe.

B. Around August 13, 2010, the Defendant received a report from the above MM office to pay the drinking value of S, which is a public official supervising the supervision of the Corporation for leisure viewing and viewing. Around August 13, 2010, the Defendant offered money and valuables to a third party for the purpose of accepting a bribe in relation to public official’s duties by transferring KRW 1,250,000 to G bank accounts in the name of foreign exchange bank.

2. Around April 2010, Defendant K listens to the horses that “it is necessary to send them to the public official in charge, who is in charge of the field work in Q from the above G at the M-site office located in Q at P, and in order to smoothly proceed with the construction work, the public official in charge of the construction supervision shall pay to G, and around April 21, 2010, the request is made to the public official in charge of the supervision of the construction works in the process of construction supervision and design change, etc., and the request is made to the public official in charge of the management of the public official in charge of the public official’s duties by remitting KRW 3.5 million to the account in the name of G foreign exchange bank.”

arrow