(영문) 대구지방법원서부지원 2019.04.24 2018가단62727
대여금
Text

1. The defendant shall pay 40 million won to the plaintiff and 15% per annum from July 6, 2009 to the day of complete payment.

Reasons

According to Gap evidence Nos. 1 through 3, it can be acknowledged that the plaintiff lent 40 million won to the defendant on July 6, 2009 by setting the repayment period to October 6, 2009 and 3% of interest per month. Thus, barring any special circumstance, the defendant is obligated to pay to the plaintiff the above 40 million won and damages for delay equivalent to the interest or interest calculated by the rate of 15% per annum within the scope of the above agreement from July 6, 2009 to the day of full payment, which is the above lending date.

Although the defendant alleged that he paid the debt, there is no evidence to acknowledge this, the defendant's argument is without merit.

If so, the plaintiff's claim shall be accepted for the reasons and it is so decided as per Disposition.