(영문) 서울중앙지방법원 2020.08.26 2019가합565668
부당이득금 반환청구의 소
Text

1. The plaintiff's primary claim and the conjunctive claim against the defendants are all dismissed.

2. The costs of lawsuit are assessed against the Plaintiff.

Reasons

1. Basic facts

A. 1) The Plaintiff is a corporation that engages in the business of selling and selling housing, the housing site development project, etc., and the Plaintiff is a corporation that engages in the business of selling and selling housing, the housing site development project, etc., and is 45,166

C Urban Development Project to develop B as housing and infrastructure by means of expropriation or use under the Urban Development Act (hereinafter “instant Project”).

(2) The Defendant Republic of Korea is the implementer of the instant project. (2) The Defendant Republic of Korea is the owner of each land listed in [Attachment 1] located in the instant project zone (hereinafter collectively referred to as “land subject to sale”; and individually, the lot number is specified only; and the Defendant Korea Asset Management Corporation (hereinafter referred to as “Defendant Corporation”) is the person delegated or delegated by the Defendant Republic of Korea with the affairs of administration and disposal of the general property owned by the Defendant Republic of Korea pursuant to Article 42(1

B. 1) Jeonnam Do Governor: With respect to the instant project, 1. The details of the authorization of the sequence 2.3: The designation of the D Urban Development Zone, the establishment of a development plan and the publication of topographic drawings on September 23, 2013 - the area of an urban development zone: 45,166 square meters: the date of public announcement of the designation of an urban development zone; 20.3 square meters on March 31, 2016; the authorization of the development plan (revision) of the E Urban Development Project and the implementation plan of Jeonnam Do on March 31, 2016 - the project implementation period of 1.3 square meters on September 23, 2013; 20.3 square meters on September 23, 2013; 20.3 square meters on December 31, 2016; 3. The alteration of the development plan (20.4 square meters on December 31, 2018).