(영문) 부산지방법원 2017.01.19 2015가합1041
공사대금
Text

1. The Defendant’s KRW 47,867,818 as well as the annual rate of KRW 6% as determined from May 15, 2014 to January 19, 2017 to the Plaintiff.

Reasons

1. Basic facts

A. On January 5, 2012, the Plaintiff entered into a contract for construction works with the Defendant (hereinafter “instant construction contract”).

The details of construction works: 316,327,190 won: 316,327,190 won, from January 6, 2012 to July 5, 2012.

B. The part related to the adjustment of the contract amount due to the extension of the construction period among the general conditions of the contract for the construction of this case (hereinafter referred to as the "general conditions of this case") which became the contents of the contract for the construction of this case is as shown in the attached Form

C. After the commencement of the instant construction project, the Plaintiff and the Defendant concluded six times the contract to modify the contract amount and extend the construction period due to changes in the construction period, design changes, etc. (hereinafter “each of the instant changes contract”).

The notice of the conclusion of each construction contract sent by the Defendant to the Plaintiff in relation to each of the instant changes is indicated below as changing the deadline for completion due to the same reasons as stated below.

On January 5, 2012, the first contract for the ground for the change of the term of completion (cost) on the date of completion of construction works: (a) the second change due to the temporary suspension of construction works on July 26, 2012; (b) January 26, 2013; (c) the second change of the term due to the cancellation of the temporary suspension of construction works; (d) January 24, 2013; (e) the change of the term of 78,514,300 won; (e) the increase of 30,00 won; (e) the increase of 30,000 won; (f) the increase of 30,000 won; (f) the new 3,000,000 won; (f) the new 3,000,000 won; (f) the new 3,030,0000 won or more; (f) the new 3,013,030,04,035,000;

C. The instant construction project is July 22, 2014.