Case Number of the immediately preceding lawsuit
Seoul High Court 2009Nu24940 ( October 31, 2010)
Case Number of the previous trial
Seoul Administrative Court 2008Guhap21089 (2009.08)
Title
The time of supply where the construction price is paid after the date of approval for use;
Summary
The supply of the service is completed and the supply price is determined as long as the construction work price to be received under the construction contract is completed and approved for use, and even if the balance of the construction work has been determined by the judgment due to the dispute arising from the defects of the service, it is only a matter concerning defects.
The decision
The contents of the decision shall be the same as attached.
Text
The appeal is dismissed.
The costs of appeal are assessed against the Plaintiff.
Reasons
All of the records of this case and the judgment of the court below and the grounds of appeal were examined, but the grounds of appeal on the grounds of appeal are not included in the grounds provided by each subparagraph of Article 4(1) of the Act on Special Cases Concerning the Procedure for Appeal, and the appeal is dismissed pursuant to Article 5 of the same Act. It is so decided as per