logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울북부지방법원 2015.10.28 2014가합5702
건물명도등
Text

1. The Plaintiff:

A. Defendant B: (a) 60.51 square meters of the first floor among the real estate listed in the separate sheet; (b)

B. Defendant C is the same list.

Reasons

1. Determination as to the cause of claim

A. 1) The Plaintiff is a housing redevelopment improvement project that has a project implementation district of the Dongdaemun-gu Seoul Metropolitan Government L 32,729.70m2 as a project implementation district (hereinafter “instant rearrangement project”).

(2) The head of the competent Gu obtained the authorization of project implementation on April 9, 2009 and the authorization of the management and disposal plan on April 14, 2014, respectively. The head of the Gu publicly notified the above management and disposal plan on April 17, 2014. (2) Defendant C was subject to cash liquidation as the owner of the real estate listed in the attached list 6, 7, Defendant I was the real estate listed in the attached list 2, 3, Defendant G was the real estate indicated in the attached list 4, 5, Defendant I was the real estate indicated in the attached list 6, 8, 9, and Defendant K was the owner of each real estate listed in the same list 10, and 11 listed in the same list.

Defendant B: (a) connects each point of indication 1, 2, 5, 6, and 1 of a map among the 60.51 square meters of the 1st floor among the real estate (owner M); and (b) Defendant D, among the 65.58 square meters of the 3rd real estate indicated in the same list on the 3rd real estate indicated in the same list, the part of the housing (A) is 27.5 square meters; and Defendant E, among the 65.58 square meters of the 1st floor of the above 3rd real estate, the part of the housing (a) connected each point of the 27.5 square meters of the 27.5 square meters of the 3rd real estate; (a) Defendant F, in order of the 2, 3, 4, 5, and 2 of the 2nd floor of the 3rd real estate; and (b) Defendant H, as of the date of closing the argument of each of the above 4th real estate leased each of the above 364th real estate.

Attached Form

Each real estate listed in the list is located within the implementation zone of the rearrangement project in this case.

3) On May 22, 2015, the Plaintiff filed an application for a ruling of expropriation with the owners of each of the above real estate, including Defendant C, to obtain a ruling of expropriation on May 22, 2015 (the date of commencement of expropriation is July 10, 2015; June 16, 2015).

arrow