Text
1. The defendant's appeal is dismissed.
2. The appeal cost (including the cost of filing an application for the return of provisional payments) shall be borne by the Defendant.
Reasons
1. Basic facts
A. The Plaintiff (Plaintiff) comprehensively succeeded to the rights and obligations of the Korea Land and Housing Corporation under the Korea Land and Housing Corporation Act on October 1, 2009.
The Korea National Housing Corporation (hereinafter referred to as the “Plaintiff”) shall not distinguish between the Plaintiff and the Korea National Housing Corporation.
(2) The Defendant is the owner of a parcel of land indicated in the column for “after partition” in attached Form 1, such as the land located in the relevant project district, which is located in the relevant project district (hereinafter “each parcel of land in this case”).
B. During the development project, the Plaintiff was finally changed to 1,747,683.7 square meters (the total area after she had been changed to 1,747,683.7 square meters) in Sinsi-si, Sinsi-si.
hereinafter referred to as “instant project district”
(2) A project to develop B as a housing site for the construction of public housing (hereinafter “instant project”).
(2) On January 18, 2007, the project of this case was designated as a Bogeumjari Housing District under the Special Act on the Construction of Bogeumjari Housing, etc., and the project of this case was designated as a Bogeumjari Housing District under Article 8(1) of the former Housing Site Development Promotion Act (amended by Act No. 8384 of Apr. 20, 2007) and approved for the development plan on Nov. 8, 2007 under Article 9(1) of the former Housing Site Development Promotion Act (amended by Act No. 9865 of Dec. 29, 2009) and thereafter, as the project of this case was converted into a Bogeumjari Housing District under the Special Act on the Construction of Bogeumjari Housing, etc., the project of this case was designated as a Bogeumjari Housing District under the Special Act on the Construction of Bogeumjari Housing, etc., and the Special Act on the Construction of Bogeumjari Housing, etc. was amended to the Special Act on Public Housing, etc. as Act No. 12251 of Jan. 14, 2014, 2014.
3. The business plan of the instant business on August 16, 2016.