(영문) 서울동부지방법원 2017.09.27 2015가단134123
소유권확인
Text

1. The claims against the Defendants by the Plaintiff (Appointed) and the Appointed F are all dismissed.

2. All the costs of lawsuit;

Reasons

1. Basic facts

A. 1) Defendants C, D, E, G, and H agreed to jointly implement the J development project with the content of creating accommodation facilities, etc. in the first place in Taecheon-do, Taecheon-si, Gangwon-do, and first, to newly construct K, L, M, N, Defendant D’s land, and accommodation facilities on the Defendant C’s O land, which is the G owner, and to this end, on March 4, 201, they registered business as P around July 4, 201 (the five of the above five of the above persons, and the Defendant B was registered as a new joint proprietor.

When 5 or less joint business operators are held simultaneously, the defendants, etc. shall be the defendants, etc.

(2) During the new construction of accommodation facilities, the Defendants, etc., at the time of the construction of the water supply facilities and electrical facilities for supplying electricity to each accommodation facility, set up the water supply system and electrical facilities on Q Q Q land, in which the Defendants, etc. shared each of 1/5 shares. On February 2, 2012, the Defendants, etc. filed an application for water supply construction and a report on the plan for electrical facility construction with the Taecheon-si and the Korea Electrical Safety Corporation in the name of P, and installed the water supply system

3) Meanwhile, Defendant C completed the registration of ownership transfer on June 18, 2012 with respect to the total of 4/5 shares of the remaining co-owners of Q land in Thai City, on the ground of division of co-ownership on June 18, 2012, and Q land became the sole ownership of Defendant C. (B) The Plaintiff, etc. acquired land and buildings owned by the Plaintiff, etc., and completed the registration of ownership transfer on April 30, 2015, after having sold land and buildings on the land from the auction procedure for real estate rent (Sacheon District Court Youngcheon Branch Branch Support R).

The Appointer F has sold the above K land and its ground buildings owned by G from the auction procedure for real estate rent (SYcheon District Court Young-gu Branch Branch Branch) and completed the registration of ownership transfer on April 1, 2015.

(hereinafter referred to as K and L land in this case, and each of the buildings in this case). 2 The appraisal reports prepared at each of the above auction procedures are each of the buildings in this case.

arrow