(영문) 서울행정법원 2020.10.29 2019구합79510
신재생에너지보급사업 참여제한처분 취소청구의 소
Text

In August 8, 2019, the defendant's disposition of restricting participation in new and renewable energy distribution projects against the plaintiff is revoked.

Reasons

1. Details of the disposition;

A. The Plaintiff, a company running a new and renewable energy-related business, a construction business, an electrical construction business, etc., completed the registration of the electrical construction business under Article 4(1) of the Electrical Construction Business Act on March 17, 2009.

The Korea Energy Corporation is a public institution established pursuant to Article 45 of the Energy Use Rationalization Act that carries out energy use rationalization projects, etc., and B is an affiliated institution established in the Korea Energy Corporation to promote the use and dissemination of new and renewable energy pursuant to Article 31 of the Act on the Promotion of the Development, Use and Diffusion of New and Renewable Energy (hereinafter “New and Renewable Energy Act”) and Article 29 of the Enforcement Decree of the Act on the Promotion of the Development, Use and Diffusion

B. From January 2014, Seoul Special Metropolitan City promoted “C Distribution Project” in accordance with Article 25 of the Seoul Special Metropolitan City Ordinance on Energy and Article 5 of the Seoul Special Metropolitan City Ordinance on the Establishment and Operation of the Climate Change Fund. The announcement of “D Business” was made on January 9, 2017, and the announcement of “E Business” on January 23, 2018.

The main contents of each of the above notices are as follows:

(hereinafter referred to as "distribution project under each of the above notices" refers to each of the following projects. D project announcement [a summary of the distribution project]: A citizen's scale desired to establish a F in a building located in Seoul Special Metropolitan City: In the case of Vietnam, citizens shall pay only the amount to be borne by the distribution company except subsidies from the total expenses, and the subsidy shall be received by the distribution company upon the consent of the applicant. The criteria for participating in the distribution company's participation in the distribution company on January 20, 2017: Obligations, such as a general company selected as a participating enterprise in the housing support project (so-called solar field) in 2017, or having experience in the solar distribution company in solar energy in Seoul Special Metropolitan City: False application for a project, such as a false seal affixed to the standard installation contract, the document alteration, the preparation of a back contract, the name of the company, etc.