(영문) 대구지방법원 2016.03.18 2014고단1571
공무상표시무효등
Text

Defendant

A shall be punished by imprisonment with prison labor for eight months and by imprisonment for four months.

However, for two years from the date this judgment becomes final and conclusive.

Reasons

Punishment of the crime

[2014 Highest 5942] - Defendant A and the Korea Electric Power Corporation, on January 7, 2009, commenced construction works for the power transmission line to supply the power transferred to the substation located in the Sung-gun area of Sung-gun, G, which was located in the Sung-Gun, and completed the construction works (excluding the foundation, assembly, and inter-line construction works) with the exception of G located in the Gyeong-do F of the 40 nuclear transmission towers, in a total of 40 transmission towers.

On the other hand, the construction was interrupted by external organizations, such as the Cheongdo Do residents and the Daegu Environmental Campaign Association, thereby obstructing the construction of the G transmission tower located in F, and the construction was suspended from July 3, 2012. On March 7, 2013, 222 organizations, such as Green Party and Daegu Environmental Campaign Association, jointly and severally formed the “The Joint Countermeasures against H transmission tower” and on April 26, 2013, residents of the 21st century continued to act against the Corporation and hold an assembly or demonstration.

On October 8, 2013, the previous year filed an application with the Daegu District Court for a disposition of obstructing the construction against the opposing residents and 23 external forces, and accepted the application for the provisional disposition on March 20, 2014, the construction was resumed from around 05:00 on July 21, 2014.

Defendants are residents of the Cheongdo and have led to the demonstration of opposition to the construction of the transmission tower with external power.

On July 21, 2014, around 07:40 on July 21, 2014, Defendants conspired and interfere with the passage of vehicles, etc. by leaving the construction site in order to prevent the construction of the transmission tower, Defendant B interfered with the passage of vehicles, etc. by hanging on the access road to the construction site. Defendant A expressed a bath to the employees of the construction site, and the Defendants interfered with the previous construction works by force between approximately 30 minutes of force until he was arrested in the act of interference with the duties of around 08:20 on the same day, due to the fact that Han River was set up in order to set up the entrance column of the construction site, and that the Defendants did not put the pole in the Gu Do Do Do , and the Defendants did not put the pole in the Gu Do , and did not put it into the entrance column of the construction site.

[2014 Highest 6169] - Defendant A’s Korea Electric Power Corporation (hereinafter “Korea Electric Power Corporation”) will be released from Gyeongnam nuclear power plant on January 7, 2009.