(영문) 청주지방법원 2018.12.20 2017가단104668
용역비
Text

1. The Defendants stated in the “personal amount” column in the attached inheritance shares table to the Plaintiff and each of them.

Reasons

1. Basic facts

A. Around October 21, 2015, the network B (hereinafter “the network”) concluded a design agreement with the Plaintiff on October 21, 2015 with respect to the construction of a new construction project (including an underground 1st floor, a total floor area of 2,400 square meters) of a ground nblet (including an additional tax) in the Seo-gu, Seo-gu, Seo-si, Seo-gu, Cheongju, which was divided into the following paragraph (d) and divided into 12520 square meters, with the Plaintiff on October 31, 2015.

B. The above contract includes the construction design cost (90,000 won per ordinary) and the civil engineering design cost (cafeteria 9 million won). The deceased provided all documents (ownership relation, etc.) necessary for building permission at the request of the Plaintiff at the request of the Plaintiff, and agreed to pay for the design work already performed if the design work is discontinued due to termination of the contract (Article 17).

C. On January 25, 2016, the Plaintiff, the Deceased, J, and K concluded a building design contract on the premise that the said M land was divided into O land for each building unit. Accordingly, the Plaintiff and the Deceased concluded a design contract on May 24, 2016 through September 30, 2016 with respect to new construction of a P building on the ground ( underground 1st floor, 953,000 square meters in total floor area, 99,00 won in the construction design cost, and 5.5 million won in the civil engineering design cost) on the construction of a new building on the ground of Seo-gu, Seo-gu, Seo-gu, Seo-gu, Seo-gu, Seo-gu.

(hereinafter “instant design contract”). D.

After that, around May 20, 2016, neighboring parks that cannot be constructed among the above M M land were left, and the constructed part was divided into 2513 square meters in O forest and field.

(hereinafter “instant site”) e.

On June 30, 2016, pursuant to the instant design contract, the Plaintiff applied for a building permit to newly build one multi-family housing (B) on the land located in Seo-gu, Seo-gu, Seo-gu, Seo-gu on behalf of the Deceased, Seo-gu, and applied for a permit to engage in development activities and a permit to convert the form and quality of the housing site into a total of 923 square meters. In addition, the Plaintiff applied for a permit to engage in development activities and a permit to convert the form and quality of the housing site among the above land

arrow