(영문) 서울중앙지방법원 2017.01.11 2016가단5118656
대여금
Text

1. The Defendants jointly and severally pay to the Plaintiff KRW 81,428,995 and KRW 45,954,491 among them.

Reasons

1. According to each of the statements in Gap evidence Nos. 1 and 3, facts such as the entry of the reasons for the claim in the annexed sheet are recognized.

Therefore, the Defendants are jointly and severally liable to pay to the Plaintiff damages for delay at an agreed rate of 25% per annum from January 29, 2016 to the date of full payment (However, Defendant B is within the limit of 76,700,000 won, which is the limit of the total amount of guarantee) with respect to KRW 81,428,995 of the balance of the principal and interest of the loan and KRW 45,954,491 of the loan principal.

2. Therefore, the Plaintiff’s claim against the Defendants is accepted in full.