logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 울산지방법원 2016.12.14 2015가합2917
매매대금
Text

1. As to KRW 224,180,00 among the Plaintiff and KRW 178,200,00, the Defendant shall pay to the Plaintiff KRW 224,200 from August 22, 2014 to April 24, 2015.

Reasons

The basic fact was that the Defendant’s North border plant produced the consortium (CON/G or C/G as one of the automatic transmission components entering a motor vehicle) and supplied it to the North Gyeongchix Co., Ltd., but it was difficult for the prime contractor to meet the supply quantity desired due to the lack of production.

Accordingly, the defendant was unable to establish a plan for installation in the Chinese factory by modifying and repairing idle facilities not used in the Ulsan factory (MCC 4 manufactured in the Japanese NISDA company).

On June 21, 2012, C Co., Ltd. (hereinafter “C”) which is an affiliate of the defendant (hereinafter “C”) entered into a contract with the Plaintiff on June 21, 2012 as “D6 CON/G D Dra,” in lieu of C, and the Defendant entered into a contract on July 12, 2012 between the Plaintiff and the Plaintiff on July 12, 2012 to repair and supply the equipment of 8 points, such as “D6 C/G D6 C/G Dra,” “O/H, etc., to the Defendant (hereinafter “instant contract”).

The down payment (30%, 243,000,000 won) determined respectively as “after the conclusion of a contract and the receipt of the Plaintiff’s claim for payment of the price,” and the intermediate payment (30%, 243,000,000 won)” and “after the receipt of the claim for payment of the price by the subject matter and the Plaintiff,” and “after the receipt of the claim for payment of the price by the subject matter and the Plaintiff,” and “after the receipt of the report for completion of the final inspection of the subject matter and the Plaintiff’s claim for payment.”

The main contents of the instant contract are as follows.

(1) The core SPEC of Section A (Provisions of the contract and the payment period) of Section A (1) shall be completed with respect to the construction project by accepting all the provisions, such as the Plaintiff’s estimate, design drawings, etc. submitted to the Defendant, including the construction contract, specifications, construction specifications, etc., as determined by the Defendant, and completing the construction project with good expertise and sincerity. (2) Materials used for the construction project shall be used as materials equal to or equal to or higher than KS specifications, and a supervisor designated by the Defendant.

arrow