(영문) 대전지방법원 서산지원 2017.02.17 2016가단52656
청구이의
Text

1. The Defendant’s Plaintiff was drafted on October 16, 2015 by a notary public, who belongs to the Seoul Central District Prosecutors’ Office.

Reasons

(b) the facts of the basis;

A. On March 11, 2015, the Plaintiff entered into a contract for construction works with the Defendant, setting the contract amount of KRW 975,00,000 (excluding value-added tax) and the contract payment period from May 10, 2015 to October 31, 2015.

Article 1 [General Conditions] 1. (Contents and Scope of the Subject Matters of the Contract) On-site installation and trial operation of Modr Facilities B, punching operations - All of prefabricated, shipping lines, trawls, Ems, engine entrance Rab), installation of all equipment and tools necessary for trial operation, and safety equipment, including all equipment and tools, etc. required for test operation (including safety equipment) production and production (2 =22 months = 120M/DAY) in the local port at the local port of port where the factory container is shut down, the upper car shall be deducted from the equipment of the excluding the upper car, the removal of the equipment, and the transfer of the factory) and Article 2 (excluding the field safety manager and the number of interpreters [a] of the contract specified by the Defendant, the Defendant shall comply with all the terms and conditions of this contract as required by the direction of the Plaintiff.

B) The Defendant shall use all the materials required under this Agreement in excess of the standard specifications or equivalents required by the mother visa, and submit to the Plaintiff upon the Plaintiff’s request, accompanied by the test report. Article 4 / [Insurance] A] The Defendant shall subscribe to an industrial accident insurance for workers’ accident compensation, and shall be liable for civil and criminal liability due to an accident.

Article 5 [Prohibition of Substitute Payment] Total Amount of Contract Deposit: advance payment of KRW 975,00,000 (VAT separately): KRW 195,00,000 (20%) shall be paid to the defendant on April 20, 2015 after receipt of performance guarantee bonds and advance payment under contract commencement deposit: (b) intermediate payment: 682,50,000 (70%) installation; (3) payment by the method of payment by the issuance of a certificate of fair rate certificate issued by the plaintiff for trial run; and (3) payment by the plaintiff to the defendant within one week after receipt of the price from the customer company (BACK-TO-BCK).

C) Balance: 97,00,000 won (10%) - all punching operations by the defendant; and