(영문) 광주지방법원순천지원 2014.10.31 2014가단5580
건물철거 및 부동산인도
Text

1. The Defendants:

(a) Attached No. 1 Appraisal Map 1, 2, 3, 4.

Reasons

1. Basic facts

A. On May 17, 2013, F delegated by the Plaintiffs: (a) the Plaintiff leased the instant land at KRW 60,500 square meters for netcheon-si E 106 square meters (hereinafter “instant land”); (b) the Plaintiff agreed to pay the remainder of KRW 14,00,000 on the same day to Defendant C for KRW 60,500; and (c) the amount of KRW 500,000 on the same day; and (d) the amount of KRW 14,00,000 on August 20, 2013.

On the other hand, when the lessee has entered into the contract, the contract deposit shall be null and void and the contract deposit shall not be claimed for the return shall be stated.

B. Defendant C did not pay the remainder, and the Plaintiff’s payment was made to F by December 2013, but did not pay it. The Plaintiffs sold the instant land to others on January 6, 2014.

다. 피고들은 이 사건 토지 위에 별지1 감정도 표시 ㄱ, ㄴ, ㄷ, ㄹ, ㅁ, ㄱ의 각 점을 순차 연결한 선내 (가)부분 53㎡ 비닐하우스, ㅂ, ㅅ, ㅇ, ㅈ, ㅂ의 각 점을 순차 연결한 선내 (나)부분 36㎡ 컨테이너, ㅊ, ㅋ, ㅌ, ㅍ, ㅊ의 각 점을 순차 연결한 선내 (다)부분 18㎡ 컨테이너, ㅎ, ㄱ’, ㄴ‘, ㄷ', ㅎ의 각 점을 순차 연결한 선내 (라)부분 18㎡ 가건물을 설치하여 G 상호로 고물상을 운영하고 있다. 라.

At the time of closing the argument of the instant land, the rent is KRW 424,600 per month (one percent per annum).

E. On April 7, 2014, the Plaintiff’s expression of intent to terminate the said lease reached the Defendants.

[In the absence of any dispute, Gap 1, 3, 4, and 8 (including each number), each entry, witness F's testimony, the result of the measurement and appraisal entrusted to the Korea Intellectual Property Corporation's office at the time of this court, the result of appraiser H's rent appraisal, the result of appraiser C's inquiry, the purport of the whole pleadings.

2. The assertion and judgment

A. According to the facts of recognition of removal and extradition request, Defendant C did not pay the remainder of rent under the above lease agreement by the end of August 20, 2013, which is the agreed date, and thereafter by December 2013, and the Plaintiffs.

arrow