(영문) 대구고등법원 2016.12.08 2015나21371
공사대금
Text

1. Of the judgment of the court of first instance, the part against the plaintiff corresponding to the money ordered to pay below shall be revoked.

The defendant.

Reasons

(b)bed.

(Evidence A No. 1-1, A 23, and 27). In addition, the phrase “the statement of the instant contract” submitted by the Plaintiff to the Defendant as of November 19, 2012 is also a special engineer.

8. Changes in the structure of steel framed works;

9. The phrase “the change in the unit of underground 1st floor (the difference in the number of iron bars and the quantity of frut)” (Evidence 20). (b) On May 6, 2013, the Plaintiff entered into the instant change contract with the Defendant (hereinafter “instant change contract”) with the following terms and conditions (Evidence 1-2 and Evidence 17). The change in the contract with respect to the original contract under Article 2(2) of the revised terms and conditions is as follows. The revised terms and conditions are as follows. The revised terms and conditions are as follows. The revised terms and conditions are as follows. The revised terms and conditions are as follows: the revised terms and conditions of the contract are set up at KRW 30,000,000 [Attachment ] of KRW 30,000,000 [Attachment ] [Attachment ] of KRW 40,000,000,000,0000,000 for the construction work to the Defendant: the new construction project owner, who submitted to the Plaintiff No. 25, on December 3, 20, 2013.

8. Changes in the structure of steel framed works;

9. The phrase “the change of the unit of underground 1st floor (the difference between the steel volume and the frupted volume)” (Evidence A 21). C. The Defendant’s payment of the construction cost and the Defendant’s payment of the construction cost in the construction site from November 29, 2012 to June 25, 2013, the Plaintiff paid the construction cost in the instant case as follows:

(No. 3 and No. 6 and No. 16). Meanwhile, until May 30, 2013, the Plaintiff carried out the instant construction work, and the Plaintiff turned down at the construction site around that time.

[Attachment Table] The amount paid on the date of payment Nos. 1, 350,000,000 March 12, 2013, 2012 (won 1, 201, 200) 60,000,000 March 29, 2013, 2003 April 23, 2013, 200,000 on April 23, 2013, 200,000,000 on May 10, 200,000 on May 16, 2013; and 60,000,006 May 20, 2013.