(영문) 인천지방법원 2016.09.09 2014가합60398
공사대금
Text

1. The Defendant’s KRW 385,637,020 as well as 5% per annum from December 12, 2014 to September 9, 2016 to the Plaintiff.

Reasons

1. Basic facts

A. On December 7, 2012, the Plaintiff entered into a contract for a construction project with the Incheon Metropolitan City Free Economic Zone Authority (hereinafter “Korea Free Economic Zone Authority”), which is affiliated with the Defendant, for the total contract amounting to KRW 5,563,491,00, and the total construction period from December 14, 2012 to December 13, 2013, with respect to the construction works for replacement facilities within the Cheongra2 District Military Units, the Plaintiff entered into a contract for a construction project with the Incheon Metropolitan City Free Economic Zone Authority (hereinafter “Korea Free Economic Zone Authority”).

(hereinafter the above construction work refers to the instant construction work, and the said construction contract is referred to as the “instant construction contract”). B.

The construction contract in this case was changed due to the change of design, extension of air period, etc. as shown below.

(hereinafter referred to as "each amendment contract" shall be defined as "the next amendment contract," and the final amendment contract as "the final amendment contract," and shall be defined as "the final amendment contract." The amendment has not been amended before and after each amendment contract, and the Corporation has been suspended before and after each amendment contract, and the period of discontinuance of the work shall also be as specified in the corresponding column 1 below.

(1) On June 19, 201, the first change of the construction period, the ground of change (unit: 1,00 won) of the date of completion of the division contract under Table 1, extended on June 19, 2013 (the extension of the construction period due to the delay of consultations in military units and the suspension of construction) 95 days prior to the first change contract (from May 1, 2013 to June 33, 2013) 5,741,563 (the change of the contract amount based on the reflection of the demand of the bridge and the military unit) 5,741,56. 2. 6. 3rd change of the construction period (the change of the construction period due to the increase of the quantity of the above wastewater treatment facilities, the installation of the construction period due to the extension of the construction period) 5,743, 384, 204. 2. 16. 4. 1. 2. 2. 2. 2. 3. 2. 2. 14. 2. 2. 201. 2. 2. 8