logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 창원지방법원 통영지원 2018.12.20 2017가합11083
공사대금
Text

1. The Defendant’s KRW 403,350,000 as well as 5% per annum from February 23, 2017 to December 20, 2018 to the Plaintiff.

Reasons

1. Facts of recognition;

A. On November 17, 2016, the Defendant (formerly: Seosung General Construction Company) concluded a construction contract (hereinafter “the instant construction contract”) with the content that the contract for construction of steel frame, board board, and Changho Construction Work (hereinafter “the instant construction work”) among the new construction works of the Gosung-gun Gyeongsung-gun Gyeongsung-gun Gyeongdong logistics warehouse (hereinafter “the instant logistics warehouse”) ordered the Plaintiff by Osung-si Gyeongsung-gun, Sungsung-gun, Sungdong-gun, and the main contents thereof are as follows.

1. Name of a master contractor: New construction of a AustriaS logistics warehouse;

2. The name of subcontracted construction works: Irons, boards, and windows from among construction works for new construction of a lux warehouse;

3. Place of construction: Acting as an agent of a high-level local government in the Seoul-gun, 111, 112;

4. Period of construction: The closing date of the sales panel on December 2, 2016, from November 16, 2016 to January 15, 2017 (Refratt air 62): January 15, 2017;

5. Contract amount: One hundred and thirty billion won per day (Won 1,430,000,000): One hundred and thirty billion won per day (Won 1,30,000,000): One hundred and thirty billion won per day (Won 1,300,000,000): One hundred and thirty million won per day (Won 130,000,000); and

6. Payment of the price;

(a) Advance payment: No one; and

2.(1) Payment of the completed portion: 10. Payment of the 20th of the following month after the end of each month; 10. Payment rate of the warranty bond and the warranty period: In the case of a complex type of work,

November, 11, 200, 200, 200, 200, 200,000,000 (3%) per each type of work, and 30,000,000 (1 day): Article 4(10/1,00,00 on the basis of the contract amount by type of work (1 day) of the special agreement (10/1,000) shall be put into work number and equipment so as not to cause any trouble in the whole air and the follow-up work, and if the construction period is delayed for more than two days, the measures shall be taken only once to submit to A (the Defendant) and the subcontract shall be taken so as not to hinder the construction period. If this is violated, the contract shall be violated.

arrow