(영문) 수원지방법원안산지원 2014.07.31 2012가합4449
손해배상(기)
Text

1. The Defendant’s KRW 31,323,242 as well as the Plaintiff’s annual rate of 5% from November 30, 2009 to April 23, 2012, and the following.

Reasons

1. Occurrence of liability for damages;

A. On November 30, 2009, at around 00:05, the Plaintiff is liable to compensate for damages. The Plaintiff is a traffic island set up at the intersection in front of the Abasi factory in front of the Abari-si (hereinafter referred to as “instant traffic island”) while operating a B B B B in the bypass of the three-lane road located in the Abari-dong, Geumcheon-gu, Seoul Metropolitan Government.

) A traffic accident was caused by the instant taxi that did not see, and the said taxi was transferred to the first place, and was caused by a traffic accident that was caused by the first place of release. (hereinafter referred to as “instant accident”).

The Defendant, who was awarded a contract for the construction of a housing site development project from the Korea Land and Housing Corporation, was performing the construction of a new intersection and road expansion in the vicinity of the said accident site, and the construction of a traffic island including the instant traffic island, and C was fully responsible for the said construction site as the Defendant D.

At that time, the new public corporation, which was awarded a contract from the Korea Land and Housing Corporation, was also selected to carry out construction work near the above accident site.

around September 2009, the Defendant temporarily suspended the construction work performed by the Defendant for the construction work of Korea-China Public Corporation. At the time of suspension, the instant traffic island was at the completion of the boundary, and left a package of the inside container.

When the Defendant ceased construction, the Defendant removed all safety facilities, such as drums, wing wing wings, etc., which were installed around the instant traffic island. At the time of the instant accident, no safety facilities were installed around the instant traffic island.

Han New Public Co., Ltd. has occupied both the lanes of the AB Bridges in the Burriside, and has temporarily changed one lane from the Burriside to the Burriside.