(영문) 창원지방법원 2018.09.21 2017나52129
공사대금
Text

1. Of the judgment of the court of first instance, the part against the defendant exceeding the following amount ordered to be paid shall be revoked.

Reasons

1. Facts of recognition;

A. On October 29, 2013, the Plaintiff entered into a contract with the Defendant for the construction of a solar power plant (hereinafter referred to as the “electric power plant construction of this case”) to reinforce the stable on the ground B in Hanam-gun, Hanam-gun (hereinafter referred to as the “the instant stable,” and the construction of reinforcement thereof as the “the instant stable reinforcement work”). The content of the contract is as follows.

Accordingly, the Plaintiff completed the instant stable reinforcement and power plant construction, and was inspected by the Korea Electrical Safety Corporation on February 13, 2014.

Standard form contract for solar subcontract construction [D each solar power plant (94.5kW)]

3. Scope of construction - All the design and installation of structures and electric installations - All the production and installation of structures - solar-powered 250Ws, rackers 100kWs - All of the rackter rooms, decentralizations - Relevant institutions and bodies including inspection of related institutions;

4. Period of construction: Commencement on November 15, 2013, and completion on February 1, 2014 (Completion of pre-use inspections)

5. Contract amount: 253,00,000 solar-powered subcontract contract (D-powered stable reinforcement works for solar power plants).

3. Scope of construction - Removal of existing roof slate and storage of wastes (site) - COLUMN floor construction works andNCHOR construction works - All manufacturing and installation of steel structures (see drawings) - Construction of board units (see drawings) - Crain contract terms and conditions (on-site use)

4. Construction period: Period of construction on November 1, 2013, completion on November 30, 2013, and on November 30, 2013: 51,700,000 won: Conditions of placing on the spot removal of wastes.

B. Meanwhile, in order for the Plaintiff to receive government subsidies from a solar power plant operator, the Plaintiff shall obtain certification from the Energy Management Corporation. However, if an employee of the Energy Management Corporation applies the rate of 1.5 times the Plaintiff’s subsidy, the wall should be installed in the instant stable. Accordingly, the Plaintiff is the Plaintiff’s installation work of the board on the outer wall of the instant stable (hereinafter “the instant stable installation work”). The Plaintiff is the “the instant stable installation work” with the cost of KRW 5,200,000, and the instant stable reinforcement work.