(영문) 광주지방법원 2017.01.13 2016가단519398
보관금
Text

1. All of the plaintiffs' claims are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

. A received;

(A) No. 15-2.3) Plaintiff C (project owner) on March 19, 2014 to E for the installation of solar power plants at the “Ksolar power plant” located in the Jeonnam-gun G on March 19, 2014 (hereinafter “instant construction”).

A) A contract was entered into with the construction cost of KRW 300,00,000 (excluding construction costs and value-added tax) (A evidence 13-1), and on May 2, 2014, with permission for solar power plants (A evidence 15-3) for solar power plants, E’s construction contract 1) around March 2014, entered into a contract with L Co., Ltd. (hereinafter “L”) (hereinafter “the instant subcontract”). The main contents of the instant subcontract are as follows.

(B) No. 1. Construction: Three solar power plants (97.02kW *3)

3. Period: From March 2014 to July 2014;

4. Details of facilities 4-1. Fix 4-4. Other construction works: The manufacture capacity of the power plant name, installation capacity, racker, racker, production capacity of power plant 97.02kW 2W 385wp 252 Kaco 33.3kW 34-2; the construction of structures, such as the manufacturing of seasonal transformation system (in the maritime volcanic type) structures, construction of structures, and racking construction, etc. according to design at the place of installation; the installation of electric structures; the installation of electric power systems (in the maritime volcanic type) shall be 4-3. Electric construction works: The racker construction, racker, earthing construction, power distribution team, power distribution team, water meter box, monitoring etc.; the installation of facilities 4-5. Rental work: the installation plan, supervision, application for rental, etc.; the installation of facilities by the Plaintiff; and the Safety Corporation shall perform the installation charges and supervision fees by the Defendant;

5. Contract amount: Total of 810,000,000 won (excluding value-added tax);

6. The land value shall be refunded on March 20, 201, 6-1. Down payment of KRW 150,000,000;

6-2.2.