Text
1. The defendant shall set forth in attached Form 6,325,342 or more of the amount of the warranty bond from the plaintiff
1. A certificate of description;
Reasons
1. Basic facts
A. On November 6, 2013, the Plaintiff entered into a subcontract (hereinafter referred to as “instant subcontract”) with the Defendant, who was awarded a contract for a new construction project on the scale B of the 15th underground floor and the 15th above ground (the 1-4th floor officetels, 5-15th apartment floor above the ground) located in Busan-gu, Busan-do and the 116,107,50 won for the construction cost (including value-added tax) among the new construction projects, and the construction cost of the 116,107,50 won for the damp-gu construction project (hereinafter referred to as “instant construction project”) and from November 6, 2013 to February 28, 2014, the Plaintiff changed the subcontract to the 137,84,750 won for the construction cost after concluding the subcontract (including value-added tax).
B. The Plaintiff completed the construction work around September 2014.
다. 원고는 2014. 9. 16. 피고의 담당자 C에게 추가공사대금 7,300만 원에 관한 견적서를 제출하였는데, 그 내역 중 미장공사는 공사면적 100평 추가, 엘리베이터 출입문, 원룸 다락 등, 501호 내지 504호 발코니문 등, 자동차출입구 벽면, 계단바닥, 각층 복도 벽면 등 미장, 계단 물받이, 샷시 창출주위 사춤, 목수하서리이고, 조적공사는 엘리베이터 출입문, 원룸 복층 사이, 501호 내지 504호 발코니문 등 변경, 자동차출입구 벽면에 대한 벽돌쌓기이다.
[Ground of recognition] Unsatisfy, entry of Gap evidence 1 to 5, purport of whole pleadings
2. The parties' assertion
A. The Plaintiff received only KRW 84,476,064 out of the principal construction cost of this case 137,84,750, and the Defendant is obligated to pay the Plaintiff the amount of the principal construction cost of KRW 53,368,686 and the amount of the additional construction cost of KRW 73,00,000,000,000,000,000 for the main construction cost of this case.
B. Of the Defendant’s principal construction cost of KRW 112,848,064, out of KRW 137,844,750 = KRW 90,848,064 paid by the trustor of the ordering authority to the Plaintiff’s 15 million paid to the Plaintiff’s Plaintiff’s husband.