(영문) 광주고등법원 2018.08.10 2017나14023
공사대금
Text

1. Of the judgment of the court of first instance, the following amounts shall be the amount ordered to be paid additionally with respect to a counterclaim:

Reasons

A principal lawsuit and counterclaim shall also be deemed a principal lawsuit and counterclaim.

1. Facts of recognition;

A. The Defendant entered into a contract with the Defendant for the road safety management office of Jeonnam-do (hereinafter “Seoul-do”), the Defendant is the Defendant’s place of business for road safety management of Jeonnam-do on December 15, 2010 (hereinafter “Seoul-do”).

(C) and “C Corporation” (hereinafter “instant Corporation”)

As to the contract amount of KRW 1,765,869,00 (including value-added tax) and the total period of construction from December 21, 2010 to December 19, 2013, the contract was concluded, and the contract was concluded again by dividing it into 123 minutes within the budget limit of Jeonnam-do. Accordingly, the details of the contract (including the increase or decrease of the cost of construction) entered into with the Defendant are as listed in the following table:

구분 계약일 공사기간 총 공사대금(원) 차수별 공사대금(원) 최초 총괄 계약 2010. 12. 15. 2010. 12. 21. ~ 2013. 12. 19. 1,765,869,000 1차분 최초 계약 2010. 12. 15. 2010. 12. 21. ~ 2011. 12. 20. 1,765,869,000 876,545,000 변경 계약 2011. 12. 22. 2010. 12. 21. ~ 2012. 2. 20. 1,860,140,000 790,630,000 준공 후 정산 결과 771,606,000 2차분 최초 계약 2012. 2. 16. 2012. 2. 22. ~ 2012. 12. 20. 1,860,140,000 772,861,000 1회 변경 2012. 7. 17. 2012. 2. 22. ~ 2012. 12. 20. 2,048,200,000 772,861,000 2회 변경 2013. 8. 12. 2012. 2. 22. ~ 2012. 12. 20. 2,387,000,000 772,861,000 최종 변경 2013. 11. 28. 2012. 2. 22. ~ 2013. 12. 20. 2,387,000,000 891,984,000 3차분 최초 계약 2013. 9. 3. 2013. 9. 4. ~ 2013. 12. 20. 2,387,000,000 723,410,000 1회 변경 2013. 12. 24. 2013. 9. 4. ~ 2014. 6. 30. 2,450,020,000 723,410,000 2회 변경 2013. 12. 31. 2013. 9. 4. ~ 2014. 6. 30. 2,533,303,000 869,713,000 3회 변경 2014. 6. 24. 2013. 9. 4. ~ 2014. 6. 30. 2,489,159,000 825,569,000 최종 변경 2014. 7. 24. 2013. 9. 4. ~ 2014. 6. 30. 2,413,836,000 750,246,000

B. On January 201, 201, the Defendant concluded a subcontract with the Plaintiff and the Defendant (the Plaintiff was changed on January 16, 201, as well as on January 16, 2012, as “stock company G,” “H,” and “stock company.”