(영문) 대구지방법원서부지원 2020.10.29 2019가합75
공사대금
Text

The defendant's KRW 168,947,300 for the plaintiff and its 6% per annum from January 11, 2019 to October 29, 2020.

Reasons

1. Basic facts

A. The Plaintiff is a company that aims at the construction business, etc., and the Defendant is a building owner who requested the Plaintiff to construct a building for the purpose of operating C Elderly Welfare Center.

Standard contract for private construction works

1. Construction name: Construction of facilities for older persons and children;

2. The construction site: D in Yong-si, Gyeongcheon-do, Chungcheongnam-do.

3. Date of commencement: April 12, 2018.

4. Date scheduled for completion: September 12, 2018.

5. Contract amount: 11. The 1/1000,000 won per day (including the value-added tax): 11. The 1/1000 attached document;

1. One copy of the general terms of a contract for private construction works;

2. One copy of the special conditions of the construction contract;

3. A copy of a design document and a calculation sheet;

B. On March 29, 2018, the Plaintiff entered into a construction contract with the Defendant for the construction of facilities for the elderly (hereinafter “instant building”) on the ground of Yongcheon-si (hereinafter “instant construction contract”) and entered into the said new construction contract (hereinafter “instant construction contract”) and entered into a special agreement on the same day (hereinafter “instant special agreement”) and attached the instant construction contract.

The main contents of the instant construction contract and special agreement are as follows.

Terms and Conditions of Contract Agreements

1. Skik of the entrance of the 1st floor (connection with the second floor of 1st floor);

2. Installation of automatic openings in each floor (1,2,3 floors) of an emergency exit;

3. Fluorical board in the ceiling of the first floor nursing test.

4. A bulletin board (or photoping) at each column side of a first floor and a water treatment room;

5. Installation of the interior fireworks of the second floor public bathus;

6. A collection room for the front part of a toilet for the first floor, for the front part of a toilet for the second floor, and for the front part of a toilet for the second floor;

7. The substitute place of work on either side of an elevator;

8. 간호스테이션 2개, 상판 인조대리석 마감(위치, 사이즈 현장 실측) ◈ 기타 모든 공사는 설계도면에 의한 작업을 우선으로 하며 내외부 마감 인테리어 마감부분 자재 선택시 건축주와 협의를 한다.

◈ 공사시 사용한 전기...