Text
1. The defendant is within seven days from the day when this judgment became final and conclusive.
(a) the lowest part of the social pages B in daily newspapers;
Reasons
1. Basic facts
(a) Details of the designation of persons eligible for preferential bargaining in the projects for construction of Class E publicity iron;
1. Project name of the project outline: E-do public-private partnership projects;
2. Qualifications of the project applicant for the main contents of the instruction for proposal - The project applicant shall be a corporation or a corporation scheduled to be incorporated - If the project applicant is comprised of not less than five investors (including prospective investors; hereinafter the same shall apply), the aggregate of the equity ratio of the preceding three investors shall be not less than 50/100, and the equity ratio of the largest three investors shall be not less than 25/100; the project applicant shall be not less than 14.5 percent of the equity ratio of the project among the investors; and the project applicant shall be a person whose equity ratio of the project is not less than 14.5 percent [Attachment 2. Business plan evaluation plan] ① The financial capacity of the investor - the person meeting all the requirements of the sub-paragraph (F) and sub-
b. In addition, the representative shall submit a written investment commitment to capital among the costs of private investment (with conditional investment commitment) and allocation - Evaluation Method - Evaluation Method: Evaluation by classifying into two stages: Evaluation by two stages only for a project applicant who has passed the first stage (pre-qualification examination, P Q) - Evaluation by two stages (technical and technical sectors) - Evaluation by the submission of a written oath, by the prior eligibility examination (P Q) and other requirements of the competent authority, and the evaluation results by classifying into two stages only for transit or deviation, and not for linking points by two stages: Evaluation by two stages - Evaluation by classifying from technology (480 points) and price (520 points): (1) The Minister of Land, Infrastructure and Transport shall promote the Edu Public Relations Project from G and H vehicle base to I (hereinafter referred to as the “instant public-private partnership Project”); and (2) Evaluation by 1,000 points in total as 1,00 points in total (520 points); and (1) Announcement by the Minister of Land, Infrastructure and Transport as the Public-private Partnership Project (hereinafter referred to as the “Public Investment Project”).
(2) The J Co., Ltd is a representative investor.