(영문) 서울중앙지방법원 2017.07.18 2016나60180
전부금
Text

1. The plaintiff's appeal is dismissed.

2. The costs of appeal shall be borne by the Plaintiff.

The purport of the claim and appeal is the purport of the appeal.

Reasons

1. Basic facts

A. The Incheon Regional Maritime Affairs and Fisheries Construction Office of the Ministry of Oceans and Fisheries (hereinafter “Korea Regional Maritime Affairs and Fisheries Office”) requested the Public Procurement Service under the jurisdiction of the Defendant to enter into a contract for container distribution construction works (hereinafter “instant construction works”). Accordingly, the Public Procurement Service under the Defendant entered into a container distribution construction contract (hereinafter “instant construction contract”) 2,520 days from the date of commencement of the construction period from the Incheon Regional Maritime Affairs and Fisheries Agency and the total construction period (hereinafter “the instant construction contract”).

On March 24, 2004, Incheon Regional Maritime Affairs and Fisheries Office 2,180,00,000 on December 31, 2004, " August 23, 2004" on March 28, 2005, "4,476,582,62, 200 on March 4, 2008, 2008, 6.3.08. 1. 1. 2, 2006. 3. 4, 2008, 206. 1. 4, 2005, 1. 2, 208, 2008, 200, 000, 00, 000, 000, 1. 1. 5, 2007, 1. 2, 2007, 207, 2008, 1. 5, 2007

The instant construction contract is a long-term continuing construction contract method (the method of adding an additional total construction amount determined by a successful bidder, etc. and concluding each contract by number within the scope of the budget for the pertinent year). The Defendant entered into a contract for construction by number of vehicles on nine occasions between treatment construction as a joint contractor, and treatment construction and comprehensive progress construction as follows:

C. 1 The subject of the container distribution construction project was changed from the Incheon Regional Maritime Affairs and Fisheries Office to Incheon Metropolitan City as the port development business was transferred to local government affairs in the construction process of the instant construction project, and each of the relevant procuring entities is the entity from the first to the seventh contract of the instant construction contract.