(영문) 수원지방법원 안산지원 2018.08.08 2018가단1605
공사대금
Text

1. The Defendants shall jointly and severally pay to the Plaintiff KRW 65,00,000 and the interest rate of KRW 15% per annum from January 3, 2018 to the date of full payment.

Reasons

According to the contents of Gap evidence Nos. 1 through 5 and the purport of the whole pleadings, the facts constituting the grounds for the claim can be acknowledged.

Therefore, the Defendants are jointly and severally liable to pay to the Plaintiff KRW 65 million (i.e., KRW 100 million - KRW 35 million) and damages for delay calculated at the rate of 15% per annum under the Act on Special Cases concerning Expedition, etc. of Legal Proceedings from January 3, 2018 to the date of full payment after the original copy of the instant payment order was served on the Defendants.

Therefore, the plaintiff's claim of this case shall be accepted on the grounds of its reasoning, and it is so decided as per Disposition.