(영문) 광주지방법원 2017.12.13 2017나50934
용역비
Text

1. The plaintiff's appeal is dismissed.

2. All the preliminary claims added by the Plaintiff in this Court are dismissed.

Reasons

1. Basic facts

A. The Defendant was awarded a contract for removal and waste disposal (hereinafter “instant construction”) among the new construction works of the Gwangju Northern District C D apartment in order to be a company engaged in the business of dismantling non-systems and structures (hereinafter “instant construction”).

The Plaintiff was a company that conducts the construction waste interim disposal business, and was in charge of the collection, transportation, and disposal of construction waste due to the instant construction work.

1. Name of construction: Removal of a new construction project of a DNA apartment;

2. Place of a construction: The day (49 parcels) of Gwangju Metropolitan City north-gu C (49 parcels).

3. Period of construction: Value of supply on September 23, 2015 to November 4, 2015: 145,000,000 won: Total amount of 14,50,000 won: 159,50,000 won (hereinafter omitted).

B. On September 23, 2015, the Defendant drafted a construction agreement (hereinafter “instant agreement”) with a limited-liability company E (hereinafter “E”) with which the instant director is a director, as follows (hereinafter “E”).

E included the removal, disposal, etc. of construction waste due to the instant construction works in the construction works to be carried out pursuant to the above agreement.

1. Name of service: Removal of a new construction project of a DNA apartment;

2. Places of discharge: Two-one parcel outside the Seoul Metropolitan City, North-gu, and 21;

3. Places of transport: Places of departure - Lots F outside 21, and - The places of destination A, both of which are located.

4. Treatment place: A (State) located in G in Jeonnam-si.

5. Settlement conditions: Cash payment within 30 days after a request for the end of each month.

6. Brokerage contract term: From September 2015 to November 15, 2015, general terms and conditions of a contract: the general terms and conditions of an attached contract shall be applied.

Construction waste mixing of waste concrete (40-01-01) 25T/D 1 80,000,000 160,000 for treatment expenses for waste disposal (40-4-14) 180,000 cubic and pulvers 30 cubic and pulvers 180,000 cubic and pulvers 920,000,000 cubic and pulvers 15,000 cubic and pulvers 12,000 cubic and pulvers (40-02-06) in cubic and pulvers 17,000 cubic and pulvers

8. 위ㆍ수탁 폐기물 및 처리금액 계약조건 ☞ ㆍ 총용역금액은 배출량에 따라 정산금액으로 추후 산정함. ㆍ 규격/단위는 수집운반차량 적재용량...