logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대전지방법원 2017.08.17 2016가합106081
손해배상(기)
Text

1. The defendants jointly do so with the plaintiff A, 165,889,200 won, and 165,889,200 won, and each of the above amounts.

Reasons

Facts of recognition

The plaintiffs are the parents of the network D (hereinafter referred to as "the network"), and the defendant Korea Housing Corporation (hereinafter referred to as the "Defendant Corporation") is designated as the implementer of the Multifunctional Administrative City Construction Project pursuant to the Special Act for the Construction of Multifunctional Administrative City in Yeongi-Gongju Area for Follow-up Measures for New Administrative Capital, and carries out design, construction, management, and supervision of the roads where the following accidents occurred (hereinafter referred to as "the roads in this case"), and the defendant C is the person who caused the accident in this case.

Around 00:30 on January 31, 2016, Defendant C, who caused the instant accident, driven the Deceased on the back-side of the Ethtob (hereinafter “the instant accident”) and driven it on the side of the Ethtoba (hereinafter “the Ethtoba”), was driving the second line 8rd line of the parking lot in front of the 4th parking lot in the lake Park, from the jurisdiction of the Prime Minister to the 4th parking lot in the lake Park, while making a left-hand turn to the Cheongju, caused an accident of falling together with the Deceased (hereinafter “the instant accident”), and the Deceased died at around 01:30 on the same day as the date of the instant accident due to the said accident.

[Ground] The plaintiffs asserted that there is no dispute, Gap evidence Nos. 1 through 3 (including a branch number; hereinafter the same shall apply), Eul evidence Nos. 1 through 11, Eul evidence Nos. 1, 2, and 11, and the purport of the whole pleadings are jointly and severally liable for damages incurred by the accident of this case, and the plaintiffs asserted that the defendants are jointly and severally liable for damages to the deceased and their bereaved families due to the accident of this case, and claim for the payment of damages incurred by the deceased's passive damages of KRW 331,112,00, 3300, 112,000, the deceased's and their bereaved families' consolation money of KRW 100,00,112,000, and damages for delay.

The Act and subordinate statutes related to negligence and causation and guidelines of the Ministry of Land, Infrastructure and Transport shall be as specified in the attached Form.

Judgment

Generally, defects in the construction, management and preservation of roads are the location of roads and the structure of roads.

arrow