(영문) 대전지방법원 2018.09.05 2017구합106540
보조금환수처분 취소 청구의 소
Text

1. The Defendant’s reimbursement disposition of KRW 7,370,132,000, which was rendered to the Plaintiff on August 8, 2017, exceeds KRW 7,000,000.

Reasons

Details of the disposition

The plaintiff, as a major pharmaceutical company, is operating the following factories (hereinafter referred to as the "factory of this case") in Ansan-si member B.

The plaintiff, around September 201, planned to transfer Plant A Port Cancer C, capsulul C, Drant Plant C's antibiotics (API) Plant Palant Palant Pest Posin (API) Plant Perant Perant Posin Synthetic (API), which is located in Ansan-gun (the plaintiff claimed that only Plant A and B factories are transferred among the factories of this case, while the defendant asserted that the factories of this case are entirely transferred, the defendant is claiming that the factories of this case are wholly located) to the Do Industrial Complex D (hereinafter referred to as "D Agricultural and Industrial Complex"), and the plaintiff submitted an application for the subsidy of KRW 19 of the Special Act on Balanced National Development, Article 17 of the former Enforcement Decree of Balanced National Development (amended by Presidential Decree No. 2441, Mar. 23, 2013) to the local government's investment subsidy of KRW 500 billion (API) and the revised subsidy of KRW 21610 billion (2.1-14 billion).

The Seoul Metropolitan Area Corporation shall file an application for subsidies for relocation of enterprises with respect to the support for investment in support for the relocation of subsidy types, or for the portion of factory (all or part of the factory) with respect to the expansion of the area of the site for a factory on the basis of the total floor area of the factory site prior to the relocation of the factory area (%) or the extension of the factory site area prior to the relocation of the factory area or the extension of the new site area (24,575.20 24,516.32 - 60,75,770,79,7079,7021, August 30, 2011 on September 30, 2011 on the date of the conclusion of the contract (pre scheduled to start the business on June 30, 2015) with respect to the commencement of the business on September 15, 2011 (pre scheduled to start the construction site) on June 30, 2011.