(영문) 대구지방법원 2018.10.05 2016가합205322
공사대금
Text

1. As to KRW 1,349,651,458 among the plaintiffs and KRW 1,203,526,930 among them, the defendant shall start from September 27, 2017, and the remainder 146.

Reasons

1. Basic facts

A. The Plaintiffs constitute a joint supply and demand organization on October 28, 2008, including the conclusion of the instant overall construction contract and each of the following numbers of vehicles, and the Plaintiffs constitute a joint supply and demand organization, and the construction work of one section out of the four-lane road package work between the Defendant and the Defendant, which is the place of the order, for the four-lane road package work (hereinafter “instant construction work”).

A) The total cost of construction is KRW 14,256,949,00 (excluding value-added tax) and the total construction period from November 3, 2008 to November 3, 2012 with respect to a long-term continuing construction contract (hereinafter “instant general construction contract”).

(2) The instant construction project was carried out by dividing into two separate contracts with a total of 12 vehicles.

(hereinafter referred to as “each of the instant contracts”). The details and details of each of the instant contracts and the amendments thereto are as follows:

1. The contract amount of 34,00,000 won for the first time on October 28, 2008: 14,265,949,00 won for the first time on November 3, 2008: The changed contract amount of 1-11 on June 22, 2009: 339,70,7000 won for the first time on June 22, 2009: 14,624: The changed contract amount of 0,00 won for the second time: 0,000 won for the first time on October 28, 2008: 14,624,00 won for the second time: The changed contract amount of 1,01,000 won for the second time: 0,000 won for the second time: 0,000 won for the first time on January 9, 200, 2014