(영문) 대전지방법원 논산지원 2018.06.07 2017가단22769
소유권이전등기
Text

1. The defendant is among 7,269 square meters of F forest in Seosan-si.

A. Each point of the table 1 to 6, and 1 attached Form A to the plaintiff A.

Reasons

1. Facts of recognition;

A. around 2015, G Co., Ltd. (hereinafter “G”) decided to carry out a new solar power plant construction project (hereinafter “instant project”) in the F Forest (hereinafter “the instant forest”) at the time Seosan City, and recruited the building owner to jointly purchase the instant forest and field and build solar power plants.

G around the beginning of April 2015, the owner of the instant project entered into a solar power plant construction contract (hereinafter “the instant construction contract”) with the Plaintiff A, C, D, the Defendant, and H (after this, Plaintiff B comprehensively succeeded to the rights and obligations of H’s business operation). Of the forest land of this case, among the forest land of this case, the owner of the instant project would build each “so-called solar solar power plant of KRW 100kWA” at the respective location determined by the owner of the instant project at KRW 225,50,000,000.

나. 이 사건 공사계약 체결 당시 공사대금은 설계, 인허가 시에 계약금 1,100만 원, 착공 시에 1차 기성금 2,255만 원, 모듈, 인버터, 구조물 출하 전에 2차 기성금 1억 6,940만 원, 준공(발전소 사용전검사 완료 시점) 후 7일 이내에 잔금 2,255만 원을 각 지급하는 것으로 정하고, 공사기간은 공사착공 협의일로부터 6개월로 정하였으며, 총 5개의 발전소 부지 중 피고의 발전소 부지는 이 사건 임야 중 별지 도면 표시 14 내지 19, 21, 20, 14의 각 점을 차례로 연결한 선내 ㈃ 부분 1,622㎡로 예정되어 있었다.

C. G has completed business registration for solar power generation in the name of the owner of the building around July 2015. A building report on the construction of Class I neighborhood living facilities (Energy supply facilities) around August 16, 2016 to the Mayor of Seosan City, was completed on August 19, 2016, and a report on the generation of scattering dust, etc. and a prior report on specific construction works, around August 19, 2016. Around August 31, 2016, after completing each report on the construction plan for electric installations, the construction plan for electric works and structures and the installation of a solar panel was completed at each power plant site, and completed solar power plants at each power plant site after completing each report on the construction plan for electric installations.