(영문) 대전지방법원 2017.03.31 2017고정165
업무상과실치상
Text

Defendant

A shall be punished by a fine for negligence of KRW 5,000,000, and by a fine of KRW 1,000,000.

The Defendants respectively.

Reasons

Punishment of the crime

Defendant

A is the representative director of E Co., Ltd. who entered into a lease contract with C and Daejeon, which is to be used at the site of new construction of a new urban residential house in Daejeon, and the defendant B is the article of a string.

Defendant

B At the construction site at the end of May, 2016, where a work is conducted using heavy objects, etc. at a high place while being engaged in the work by using a stringr at the upper end of the construction site at the work site at the end of May, 2016, the boom (the vertical axis part) and the boom [the part of the boom or the boom [the part of the boom which is going going across by a road in the upper part of the boom and is ordinarily used for the transfer of goods at the end of the boom], the boom water (the part of the booming part which is going outside by a road in the upper end of the boom), and the boom (the part of the boom boom boom boom boom boom boom boom boom boom boom boom boom boom boom boom boom

He discovered that he had become old and that he was in need of the replacement of the excessive language to F and the defendant A.

The overwork of boomers play a role in the fixing of trawls, drillings, etc. In the event that overwork is broken out, a balanced trend that booms the balance of booms may occur, and as a result, there is a concern that the boom booms that lose balance falls on the ground and passing through the on-site workers' and the field surrounding the booms, etc. Therefore, if it becomes known that there is anything wrong in overwork as above, the overwork booms shall immediately inform this fact to the manager of the booms and stop the work using the booms, while the manager and the person in charge of the construction site of the booms shall not perform the work until the safety of the booms is replaced by the overwork of the booms.

Nevertheless, it is not appropriate.