(영문) 서울중앙지방법원 2017.06.27 2016가합517224
손해배상(기)
Text

1. The Defendant’s KRW 165,971,525 for the Plaintiff and 5% per annum from May 4, 2015 to June 27, 2017.

Reasons

1. Basic facts

A. The status of the parties is a corporation with the purpose of developing and selling semiconductor display devices, etc., and the Defendant (the former trade name: Hyundai Putotomob Korea Co., Ltd.; hereinafter “Defendant”) is a corporation engaged in the business of manufacturing and selling electronic devices, electric wires, etc.

B. The Defendant’s new project implementation, etc. 1) The Defendant is only a device to prevent electric accidents caused by various electric components used for automobiles in calculating the distribution state through the periodic monitoring of the distribution of a new IBS device (hereinafter “IBS device”) while seeking for a new project implementation around December 2014. The Defendant is only called “IBS device” (hereinafter “instant project”). Recognizing the fact that the producer is found, the IBS device development project (hereinafter “instant project”).

(2) Around December 2014, the Defendant entered into a consulting agreement with Albnbnb Partners on the business feasibility review of the instant project and the selection of a development cooperation company for the establishment of automation process. Abnbnb Partners Co., Ltd selected the Plaintiff as a cooperation company for the IBS assembly process and recommended several relevant companies to the Defendant.

3) From around December 4, 2014, the Defendant, along with development cooperation companies, including the Plaintiff, had a meeting with the content of the process design and the design of the automation equipment design for the construction of the automation process of the instant project. The Plaintiff, in consultation with the Defendant’s employees, performed relevant duties, such as the development and sampling production of the IBS assembly. (C) On May 4, 2015, the Defendant notified the Plaintiff that the instant project was suspended due to internal conditions.

2 The Plaintiff is the Defendant on May 8, 2015 and May 19, 2015.