(영문) 부산지방법원 2019.07.26 2019구합20618
부실벌점부과처분 취소
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

Details of the disposition

The Plaintiff is a corporation that has been engaged in the business of construction design and construction supervision since February 1, 1994, and from around 1996, as a construction project management service provider, the Plaintiff is a corporation that has been engaged in the business of construction planning and construction supervision, and as a construction project management service provider, the Plaintiff is responsible for supervision with respect to the “D new apartment construction construction project” (hereinafter “instant construction project”) performed between January 12, 2017 and August 31, 2019 on the six parcels outside C in the city of literature.

- Items omitted and quality tests not conducted: gas pressure - Details adjacent to iron bars constructed at the columns and beams of G-dong underground parking lots: External inspection (for each page of D19, 22,25) for steel bars constructed at the columns and beams, and internal defects and seal testing (500 units), but the testing is not conducted. - From August 27, 2018 to September 28, 2018, the Busan Regional Land Management Office, such as concrete rupture repair materials, asphalt containers scheduled to be packed on the spot, etc., issued a certificate of quality inspection by the construction engineer at the construction site at the construction site at the time of the instant construction site at the time of the instant construction site (hereinafter “the instant site inspection”) and obtained confirmation from the supervisor at the construction site at the time of the instant construction site at the time of the instant construction site at the time, and obtained confirmation from the supervisor at the construction site at the time of the instant construction site at the time of the instant construction site at the time of the completion of the construction site at the time of the construction site at 20.

On October 15, 2018, the Defendant notified the Plaintiff of the instant construction site inspection results and corrective orders (hereinafter “instant on-site inspection results”) with the following descriptions as to the matters pointed out in the instant on-site inspection.

The name of construction - the project owner (project owner) - the construction project management company - the new construction project by the construction project management company (type D) - H construction project - the Plaintiff’s title: