Text
1. The Defendant’s KRW 2,245,725,638 as well as the Plaintiff’s KRW 6% per annum from July 6, 2016 to February 1, 2018.
Reasons
1. Basic facts
A. The conclusion of the instant construction contract and extension of the construction period; 1) The National Armed Forces Contract Official belonging to the Armed Forces of the Armed Forces, an affiliated organization of the Defendant, is the Armed Forces, on August 30, 2012, “A Facility Corporation” (hereinafter “instant construction”).
(2) As to the instant construction work on November 14, 2012, the Plaintiff concluded a comprehensive contract for construction work in the form of long-term continuing construction contract between November 14, 2012 and May 13, 2014, with an estimated price of KRW 34,457,760,00, and the construction period of KRW 26 months from the contract date. The Plaintiff concluded a comprehensive contract for construction work in the form of long-term continuing construction contract from November 14, 2012 to May 13, 2014 with an estimated price of KRW 11,95,00,000 and the construction period of KRW 14,719,48,830 from November 14, 2012 to January 13, 2015.
After that, the Plaintiff and the Armed Forces Finance Management Body concluded each of the following contracts and amendments as stated in Table 1:
(hereinafter referred to as the “instant construction contract”) concluded each of the instant construction contract, including the instant overall construction contract and the instant multiple contracts, respectively.
3) Each modified contract set forth below [Attachment 1] (hereinafter referred to as “Classification”) shall be “the next modified contract” as indicated below.
The total construction period of the instant construction contract and the construction period by the number of teas according to the instant contract under the first, fourth, or sixth amendment contract was extended as indicated in the respective corresponding part of the construction contract (hereinafter “non-fixed”) and “total construction period by the number of teas” were extended as indicated in the pertinent part.
(1) As classified, the total construction period for each total construction period for each unit of tea (cost) contract date and the total construction amount for each unit of tea (cost) contract shall be overall, and the total construction amount for each unit of tea contract shall be 1,95,00,000 on November 14, 2012 to May 13, 2014 to 23,719,48,830 on November 14, 2012 to 14, 130 on January 14, 2015 to 130 on January 13, 2015; 10,95,00,00 on October 14, 2012 to 14, 2015; 20,000 from November 23, 2014 to 14, 2014 to 20,000 on November 14, 2014 to 208;