1. All of the plaintiffs' primary claims and conjunctive claims are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. The Forest Survey Division of the Gyeonggi-do Forest Survey Division of the Gyeonggi-gun K-gun, which was prepared during the Japanese occupation period of the foundation fact-based fact-based fact-based fact-based fact-based fact-based fact-based, states that M et al. and 5 other than M, who had an address in Yangju-gun Lri in Gyeonggi-do, were jointly informed of the fact-finding 10 YY 6 YYY

The land before the division of this case was divided into the O forest, P forest, and Q forest in the Gyeonggi Yang-gun. Among this, the P forest was subdivided into the P forest and R forest again, and the P forest was subdivided into 90 square meters before the S.

Before S, around September 20, 1974, 90 square meters was divided into 65 square meters before S and 25 square meters before T.

With respect to the above S 65 square meters, on December 16, 1974, the registration of ownership preservation was made in the future of the defendant Republic of Korea on December 26, 1974, and thereafter the registration of ownership transfer was again made in the U.S. on December 26, 1974, and the above T 25 square meters was caused by the conversion of area, administrative district, etc., and the registration of ownership preservation was made in the future of the defendant Republic of Korea on July 2, 1980.

The above 65 square meters was 129 square meters in Guri-si and 86 square meters in Guri-si prior to Z due to the conversion of area, division, change of land category, and change of administrative district. The above 129 square meters in Guri-si prior to Z-si around September 2, 1991 by means of a land substitution disposition under the division arrangement, and the above 86 square meters in Guri-si was 122 square meters in Guri-si and 120.4 square meters in Guri-si (hereinafter “instant 1 land”). On April 21, 1990, the above 86 square meters in Guri-si was incorporated into 122 square meters in Guri-si and 183 square meters in Guri-si (hereinafter “instant 2 land”). The above 83 square meters in Guri-si prior to 203 square meters in Guri-si was incorporated into 392 square meters in each of the instant land (hereinafter “the instant land”).

On the contrary, the Defendant’s assertion in the Republic of Korea is accepted to the effect that the entire area of 83 square meters prior to Y is not incorporated into the instant three land.