(영문) 서울고등법원 2016.06.02 2014누48919
시정명령및과징금납부명령취소
Text

1. On April 10, 2014, the Defendant’s corrective order and penalty surcharge payment order issued to the Plaintiff via Resolution B shall be revoked.

Reasons

Basic Facts

The status of the plaintiff et al., the plaintiff corporation C (hereinafter referred to as "C"), D, E, F, G, H, and I are those engaged in construction business, and when they are collectively referred to as "eights such as the plaintiff et al." under Article 2 (1) of the Monopoly Regulation and Fair Trade Act, and "sixs such as the plaintiff et al." among them are referred to as "sixs such as the plaintiff et al.".

applicable to this section.

J The summary of the construction works is "K et al. of this case".

A large-scale housing development project is a project promoted and ordered for the purpose of promoting balanced regional development in connection with the construction of urban railroad system in connection with existing subway 1 and 2, and the promotion of regional development. It is a large-scale construction project that is first built on the route of 23.95 km in length on the first day in Korea where 30 stops are located.

L on December 15, 2008, upon receipt of a contract from the instant ordering office, divided into Section 1 into eight sections from Section 8 to Section 8, and notified the public announcement of the tender. The instant construction is called “instant construction” and “the instant tender” when referring to the bidding procedure.

Of them, the main contents of the public announcement of the tender for the fourth section (M section) construction works are as follows. The public announcement of the tender for the construction works of J 4 Section (M section): K construction site: The public announcement of the tender for the construction works of J 4 Section (M section): The public announcement of the tender: the tender for the construction works of J 4 Section (M section): the alternative tender (75% of the design score), weight standard method (price 25%) (price 25%): the estimated construction period of KRW 117,987,00,000 (including value-added tax): the design period of 1,825 days from the commencement date of the construction - the tender for the alternative design period of this case is 100 days from the site site date stipulated in Chapter 6, Articles 78 and 79 of the Enforcement Decree of the State Contracts Act.