(영문) 전주지방법원 2020.09.09 2018가단30674
공사대금
Text

1. The Plaintiff (Counterclaim Defendant) shall pay to the Defendant (Counterclaim Plaintiff) KRW 40,126,340 and its payment from October 26, 2019.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. Place and name of a basic construction: The type of construction work 1: the period from September 1, 2018 to January 30, 2019: The period of construction work 95 million won (including value-added tax): 3,60,000 won (including value-added tax): Electrical construction 9 million won (including value-added tax) and other types of construction work 1: 1: 10% of the payment terms for the construction cost for the unit of 95,000 won (10 square meters) and 30% of the date of construction work for the unit of 1: 30% of the date of construction work for the unit of 30% of the date of construction work for the unit of YY-gu C Multi-use Multi-use Housing : 20% of the date of construction work for each unit of 1: 20% of the date of construction work for the unit of 30% of the building: 20% of the date of construction for the unit of 3rd concrete 3: 20% of the building date;

The construction type 2: The terms and conditions for the payment of construction cost (based on 24 pages) for the construction work units of 3,60,000 won: 50% of the construction completion: 50% of the construction completion: The whole construction related to the waterworks and sewerage facilities shall be the responsibility of the construction executor, but the payment shall be borne by the construction owner.

After the completion of construction by 50%, 50% special items: The whole of the construction related to telecommunication shall be the responsibility of the contractor, but the payment shall be borne by the owner of the building.

It does not include electricity related to the interior of the Republic of Korea

A. On September 5, 2018, the Plaintiff: (a) received a pelvis, facility, and electrical construction (hereinafter “instant construction”) from the Defendant among multi-unit housing construction works located in the Jeonsan-gu Seoul Special Metropolitan City; and (b) concluded the instant construction contract with the Defendant as follows (hereinafter “instant construction contract”).

B. The Plaintiff’s instant case around September 6, 2018.