logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대전지방법원논산지원 2019.06.13 2018가단20326
건물등철거
Text

1. The Defendant (Counterclaim Plaintiff) against the Plaintiff (Counterclaim Defendant)

(a) Attached Form 1 appraisal of the land listed in paragraph 1 of the attached Table;

Reasons

1. Facts of recognition;

A. Ownership change 1) On March 1, 193, 193 with respect to the 2nd 4th mal of the forest E, Chungcheongnam-gun, Chungcheongnam-do, the registration of ownership transfer was made under the name of F on the same day. On June 30, 1970, the registration of ownership transfer was made under the name of H on October 10, 1959. The said forest was registered in installments on May 25, 1994 (hereinafter “the instant forest”) with the said D forest land 1,587 square meters (hereinafter “the instant forest”) and 813 square meters of the I forest, and the said I forest land was changed to C large 813 square meters of the said land on the same day (hereinafter “the instant land”).

3) Since May 25, 1994, the registration of ownership transfer was filed under the name of J on July 5, 1969 with respect to the instant land and forest land. However, on the ground of donation on March 17, 2003, the registration of ownership transfer was filed in the Plaintiff’s name. (B) The Defendant occupied and used the instant land and forest, and owned the registration of ownership transfer on April 26, 1995, with respect to the 175 square meters (hereinafter “the instant land owned by the Defendant”).

2) The Defendant is residing on the ground of the instant land owned by the Defendant, and the relevant housing area is located in one square meter (hereinafter collectively referred to as “instant bedroom”) in the area77 in the ship connecting each point of 3 square meters of the housing area on the part of6 in the ship connecting each point of 41, 42, 43, and 41 indicated in the attached drawing among the foregoing housing area, and 44, 45, 46, and 44 in the attached drawing.

(3) The Defendant is installing the instant forest by cutting down the instant forest and field. 3) The Defendant, in turn, connects each point of 16m2, 17, 9, 18, 19, 20, 16m2, 24m2, 22, 23, 21m2, 24, and 21m3, 1m2, 25, 26, 27, 27, 28, 28, 28, 24, 16 on the ground of the instant land, in order to connect each point of 12, 13, 14, 15, and 12 of the attached drawing indicating the attached drawing to the instant land and the instant forest and each point of 25,26, 27, 27, and 288.

arrow