(영문) 서울행정법원 2015.01.22 2014구합61118
손실보상금
Text

1. The Defendant’s KRW 63,530,010 as well as the Plaintiff’s annual rate from October 12, 2013 to January 22, 2015, and the following.

Reasons

- Adjudication on expropriation on August 23, 2013 by the local Land Tribunal of Jongno-gu Seoul Metropolitan Government on September 24, 2010 - Adjudication on expropriation: Jongno-gu Seoul Metropolitan Government D-181.80§³ (hereinafter “instant land”) and its ground (hereinafter “instant building”) owned by the Plaintiff on September 11, 2013: Compensation: 1,737,781,790 won (the instant land 1,591,395,390 won) - The appraisal corporation shall be deemed to be “appraisal on expropriation,” and the appraisal corporation shall be deemed to be “appraisal on expropriation,” the appraisal corporation and Onnuri appraisal corporation (hereinafter “adjudication on expropriation”): The appraisal corporation shall be deemed to be “appraisal on expropriation,” the appraisal corporation’s overall appraisal area shall be deemed to be 1,591,395,390 won and the appraisal corporation’s overall appraisal area shall be deemed to be 50/160,000 won or less; the appraisal corporation’s appraisal corporation shall be deemed to be 506/16/16/16/6/7

A vehicle access can be made to the land and the surrounding areas of the instant building and the connection between accessibility to the south and the city center and adjacent areas depending on unification is good.

As a result of the appraisal of the expropriation ruling and the objection ruling, the expropriation ruling and the appraisal appraiser selected the land of this case as a comparative standard for the F land of Seodaemun-gu Seoul as a public announcement of the public announcement of the project approval, and reflect the land fluctuation rate up to August 23, 2013, which is the date of the expropriation ruling, on the public announcement of the land price as of January 1, 2010, which is nearest at the time of the public announcement of the project approval.