(영문) 서울행정법원 2014.07.17 2013구합1041
수용보상금증액
Text

1. The defendant,

A. 1,288,380 won to Plaintiff A, 7,649,530 won to Plaintiff B, 26,021,450 won to Plaintiff C, and Plaintiff G.

Reasons

The execution plan of the adjudication and the name of the project (hereinafter collectively referred to as "project in this case") among the following projects - Railroad construction projects [the primary project (hereinafter referred to as "first project") - Railroad construction projects [the public announcement of implementation plans for the construction of high-speed railroads in the Seoul Metropolitan area (hereinafter referred to as "second project") - Public announcement of implementation plans for the construction of high-speed railroads in the Seoul Metropolitan area (hereinafter referred to as "the second project") shall be made on May 27, 2011, public notification of the Ministry of Land, Transport and Maritime Affairs No. 2011-246, and public notification of the Ministry of Land, Transport and Maritime Affairs No. 201-746, Feb. 17, 2012; hereinafter referred to as "the first adjudication on expropriation"): The relevant land subject to expropriation shall be listed in the list of the relevant land subject to expropriation in annexed Table 10 to 210: - The list of the relevant land subject to expropriation as stated in annexed Table 1116:

The Central Land Tribunal's ruling of expropriation (related to the first project) on October 19, 2012 - Compensation for losses: The relevant amount in the column for the ruling of expropriation (related to the second project) recorded in the list of the objects of expropriation listed in the annexed Table 11 - The adjudication of expropriation (related to the second project) on December 14, 2012 - The adjudication of compensation for losses listed in the annexed list 1 to 10 is each corresponding amount: the appraisal corporation of each corresponding amount: the appraisal corporation at sight and the central appraisal corporation below.

arrow