(영문) 청주지방법원 2017.07.12 2016가합773
추심금
Text

1. As of September 24, 2015, SPS Co., Ltd. with respect to each contract listed in the separate sheet against the Defendant.

Reasons

1. The underlying facts of the instant case are based on the NAEex Co., Ltd. (hereinafter “A”) and the EP system (hereinafter “B”) enter into a contract for the new purchase of X100PNL INR & W/ HS COMINE LINE JG as follows:

Section 2 (Contract Amount) Contract Amount: Won Sheet 580,000,000 (Won 580,000,000 additional tax) Amounting to 30% of the 174,000 174,000,000 of the first intermediate payment at the time of payment at the time of the preparation of the first installment payment contract, 116,000,000 of the second intermediate payment at the time of the establishment of LINE, 20% of the second intermediate payment at 116,00,000 of the second intermediate payment at the time of completion of production 16,00,000 the remaining amount at the time of the completion of the production of the first installment payment at 1 month after the first half payment at the time of 1 month after the first half payment at the time of 580,000,000 regular installment payment (the time of delivery)

1. B shall be supplied in accordance with all the matters indicated in the purchase specifications, specifications, etc. and shall be installed not later than September 30, 2014;

2. When Eul supplies the goods, the completion thereof shall be notified to Gap.

Article 5 (Place of Delivery) The place of delivery of contract products shall be the designated place of A.

Article 7 (Inspection and Trial Operation)

1. B shall undergo an inspection by a supervisor designated by A and a supervisor designated by B, and if he/she fails to pass it, he/she shall undergo an inspection again by manufacturing or replacing it with his/her responsibility and expenses, and any delay in supply resulting therefrom shall be governed by B;

On July 16, 2014, the Defendant entered into each of the contracts listed in the separate sheet (hereinafter referred to as “instant contract”) with EPS Co., Ltd. (hereinafter referred to as “PS system”) (hereinafter referred to as “instant contract”) and the contract listed in the separate sheet No. 1 and the separate sheet No. 2 (hereinafter referred to as “instant contract”). The main contents are as follows.

The contract No. 2 of the instant case entered into a purchase contract for the installation of X100 Q&T LINE LINE LOBG BaDD (hereinafter “B”) and the PS system (hereinafter “B”) as follows.

Article 2 (Contract Amount) Contract amount: Commination of the total amount of money in full.