Text
1. The plaintiffs' primary claim and the conjunctive claim are all dismissed.
2. The costs of lawsuit are assessed against the plaintiffs.
Reasons
Basic Facts
Plaintiff
A was the owner of each real estate listed in the attached Table 1 List, and the Plaintiff B was the owner of each real estate listed in the attached Table 2 List of Real Estate (hereinafter referred to as “each land of this case”).
1. Name of industrial complex: E industrial complex;
2. Location and area of the industrial complex;
(a) Location: ASEAN-si, H, and Iririwon in Chungcheongnam-do; and
(b) Area: 2,113,759 square meters (639,409 square meters);
3. Promotion of balanced regional development through the efficient supply of industrial sites and the reasonable placement of industries through the creation of local industrial complexes meeting the openings of high-speed railroads with the aim of enhancing national competitiveness through the creation of high-tech new industrial complexes in the 21st century type, and the balanced development of national land, and the development of high-tech knowledge industry by creating a cluster centered on electronic and information machinery and industry-oriented industrial complexes contributing to the revitalization
4. An operator of an industrial complex development project;
(a) Address: Suwon-si in Gyeonggi-do;
(b) Project operator: K representative L;
5. Period and method of development of the industrial complex;
A. Period of development: on August 5, 2004 to 2009 (hereinafter omitted), the Chungcheongnam-do Governor designated, approved, and announced the following E industrial complex D on August 5, 2004. On May 28, 2005, the implementation plan of the E industrial complex was approved and announced as F on May 28, 2005.
1. Name of industrial complex: M industrial complex;
2. Location and area of an industrial complex: 2,095,062 square meters in the area of Hri-ri and Iri-ri, Chungcheongnam-do, Chungcheongnam-do.
3. Promotion of balanced regional development through the efficient supply of industrial sites and the reasonable placement of industries through the creation of local industrial complexes meeting the openings of high-speed railroads with the aim of enhancing national competitiveness through the creation of high-tech new industrial complexes in the 21st century type, and the balanced development of national land, and the development of high-tech knowledge industry by creating a cluster centered on electronic and information machinery and industry-oriented industrial complexes contributing to the revitalization
4. Project operator of an industrial complex development project: Defendant; and