(영문) 서울고등법원 2015.04.16 2013나35810
용역비
Text

1. Of the judgment of the court of first instance, the part against the defendant in excess of the amount ordered to be paid below shall be cancelled.

Reasons

1. Name of service in a service contract of a district unit planning (class II district unit planning): The area applied for the development project of a high-tech industrial complex (class II district unit planning): The service period of KRW 900,000,000 (excluding value-added tax): the contract date between Class II and Class II district unit planning zone: the purpose is to faithfully implement the contract documents by setting necessary matters according to the approval for the determination of a district unit planning under the administrative law and the implementation thereof;

Article 2 (Scope of Services and Services) The Plaintiff shall, at the direction of the Defendant, complete this service in a efficient and sincere manner within the scope of the above contract amount by dividing it into one step and two steps, and the Plaintiff shall perform minor changes or minor matters not specified in this contract without changing the contract amount.

(1) In principle, Article 3 (Period of Application for Approval)(2) of the Act, such as surveys on current status of the first phase (based on district unit planning), urban management planning-based drawings, preliminary examination reports, land suitability assessment, infrastructure plans (basic plans), landscape impact assessment plans, factors influencing disasters, cultural heritage surface surveys, traffic impact assessment, approval of Class 2 district unit planning, etc., shall be subject to the approval authority in accordance with the schedule of service progress table attached to which the Plaintiff has consulted with the Plaintiff, and each of the following subparagraphs shall not be included in the period:

Provided, That the second step may vary according to the development plan, so the plaintiff and the defendant shall be determined through consultation.

(1) In the event of a change at the Defendant’s request during the performance of this service, (2) in the event of a delay in an investigation due to a natural disaster, 30% shall be paid at the time of entering into a contract with advance payment under Article 4 (Price Payment), and the balance shall be paid in full at the time of completion of this service (approval).

Provided, That the second-stage shop design.