Text
1. The Plaintiff:
A. Defendant B’s KRW 16,813,535 as well as 5% per annum from April 25, 2017 to May 25, 2017.
Reasons
1. Determination as to the claim against the defendant B
A. Determination 1 as to the cause of the claim 1) In full view of the facts acknowledged as Gap evidence No. 1, Gap evidence No. 2, Gap evidence No. 4, Gap evidence No. 6 through 9 (including each number), and the overall purport of the pleadings as a result of the fact-finding with respect to the head of the public interest center in the Sinju-si, the court below held that, around 2012, the plaintiff was a new construction corporation (a total floor area of 91.2 square meters; hereinafter referred to as "the first new construction corporation of this case") in the non-party No. 4 and one lot of land (a total floor area of 91.2 square meters);
(E) New construction works for neighborhood living facilities (retail stores) on land outside E and one parcel (total floor area of 481.6m2, hereinafter referred to as “new construction works in this case”)
() After entering into a design and supervision contract with regard to the construction work of this case, the service such as preparing and submitting design drawings on August 2012 is completed, and around November 8, 2012, the construction permission was obtained from the petitioner head of the Gun, and the Plaintiff was not paid each construction design cost to the Plaintiff (hereinafter “new construction contract of this case”). Accordingly, in order to ensure the contractual relationship between Defendant B and Defendant B around November 21, 2014, the contract amount is KRW 10,500,00 (including additional tax), construction supervision cost, KRW 7,960,00 (including additional tax), and the contract period is from November 201, 2014 to the completion of construction work (12 months after commencement).
A) A contract is concluded with respect to the instant 2-built construction project, the contract amount of which is KRW 5,070,00 (including value added tax), construction supervision cost of KRW 4,370,00 (including value added tax), and the contract period of which is determined from November 2014 to completion of the construction project (12 months after commencement) (hereinafter “new construction contract of this case”).
B A. A. B: (a) around November 28, 2014, submitted a construction report on the commencement of the construction works of this case to the Public Interest Service in the Public Interest Service in the Public Interest Service in the Public Interest Service in the Public Interest Service in the Public Interest Service in the Public Interest Service in the Public Interest Service in the Public Interest Service (hereinafter “Public Interest Service”); (b) but (c) performed only the suspension work even after the submission thereof.