Text
Defendant
A A Fine of KRW 15,00,000, KRW 70,000, KRW 70,000, KRW 00, KRW 000, KRW 10,000, KRW 10,00.
Reasons
Punishment of the crime
[Status and duties of Defendant A] From early 2007 to November 201, 2010, Defendant A worked as the managing director of the Civil Work Headquarters B (former NN Co., Ltd.; hereinafter “B”). Defendant C is the managing director of D Co., Ltd. (hereinafter “D”) from January 24, 2005 to the end. Defendant E is the managing director of D Co., Ltd. from May 1, 2008 to December 31, 2012. Defendant E is the managing director of F Co., Ltd. (former O Co., Ltd.; hereinafter “F”), who worked as the managing director of the business team of F Co., Ltd. (former Co., Ltd.) from May 1, 2008 to December 31, 2012. Each of them served as the managing director of the F Co., Ltd. (hereinafter “F”).
Defendant
B, Defendant D, and Defendant F are corporations entities whose main business purposes are each construction business.
[Basic Facts] Three executives in charge of receiving orders from government-funded construction companies B P, Defendant C, and Defendant E (hereinafter “instant construction”) shall hold several meetings at the subway shop near the subway Station in Dongjak-gu Seoul Metropolitan Government on or before the end of December 2009, and the Public Procurement Service shall, at the request of Q on or around October 23 of the same year, publicly announce the bidding by “R (the method of selecting a bidder who receives the highest points after adding the highest points to the prices (minimum 50%) and design fields (design Examination, 50%) as a successful bidder at the request of the Public Procurement Service [the method of selecting a bidder who receives the highest points as a successful bidder]” (hereinafter “the instant construction”) in relation to the bidding by the public tender of the public service company P, Defendant C, and Defendant E (hereinafter “the construction in question”), by fixing the price bid price by mutual agreement, and by considering the cost of the construction work (the bid price estimate to be lower than 10% compared to the tender price at the above 90% lower than the tender price (the bid price at the above).5%.5%.