(영문) 서울중앙지방법원 2016.05.12 2013가합537128
공사대금등
Text

1. The Defendant’s KRW 292,205,964 among the Plaintiff and KRW 242,205,964 among the Plaintiff, shall be KRW 50,00,000 from March 14, 2012.

Reasons

1. Basic facts

A. 1) The Plaintiff is a company that runs the construction business, etc., and the Defendant is a corporation that is engaged in the joint production, processing, sale, and distribution business of fishery products. B as the Defendant’s director, the Plaintiff was in charge of all the duties while carrying out the business since the establishment of the Defendant. 2) On July 29, 2011, the Plaintiff completed the construction work that newly constructs Kim-Processed Factory (including one unit factory building and Kim Cleaning; hereinafter “instant factory”) on the ground of Chungcheongnam-gun, Chungcheongnam-gun, Chungcheongnam-gun, Seoul (including one unit factory building and Kim Cleaning; hereinafter “instant factory”) with the construction cost fixed at KRW 649,00,00 (including value-added tax) for the construction period from August 1, 201 to October 15, 2011 (hereinafter “instant contract”).

B. On June 30, 201, the Defendant obtained a construction permit on one unit of factory buildings with a height of 11.82 meters from the building area, 97.5 square meters, 97.5 square meters (1st 977.5 square meters) among the instant factories, and obtained a construction permit on one unit of factory buildings with a height of 11.82 square meters. On July 201, the Defendant obtained a construction permit on the change of land form and quality and installation of structures for the creation of the instant factory site for the instant factory site (2,259 square meters) on October 25, 201. The Defendant obtained a construction permit on the instant factory building area, 1,254 square meters, total floor area of 1,702.76 square meters (1st 98 square meters, 22.76 square meters, 14.76 square meters, 2012 square meters, and 2084 square meters from the installation of a structure, 2016.75 square meters.7.74

3) On December 16, 201, the Defendant received a certificate of completion inspection on the above development activities from the head of Seocheon-gu, and received a letter of approval for use on the factory building on the 30th day of the same month. [Grounds for recognition] The fact that there is no dispute, Gap evidence 1, 5, 11-3, 28 through 34 (including each number of branches), respectively.