Text
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
(b) Seoul B police station;
1. Tender outlined contract method: General competition/qualification test method: Time limit for the supply of gas engines pumps: June 30, 2017: Estimated price for the lower portion of the delivery place: 387,233,400 won (Additional tax separately);
3. 입찰 참가자격 ◐ 본 건은 서울B경찰서의 요청에 따라 C 주식회사(이하 ‘C’라 한다)의 제품으로 납품하여야 하오니 반드시 첨부된 특정규격사유서를 확인 후 입찰에 참여하여 주시기 바랍니다.
4. 주요 공지사항 ◐ 예정가격 * 본 입찰의 예정가격은 15개의 예비가격 중(기초금액의 ±2% 범위) 4개를 추첨하여 산술평균한 가격으로 결정되며, 예비가격 산출을 위한 기초금액은 전자입찰서 접수개시일 전일에 국가종합전자조달시스템에 공개합니다.
* The tender will be a tender to which multiple preliminary prices apply and will be less than the calculated maximum number of reserve prices.
* The maximum acceptance price of tenders covered by the State Contracts Act is 102% of the basic amount, and 103% of the basic amount for tenders covered by the Local Contract Act.
* The bidder is not allowed to submit a tender in the event of a bid and a bid before the basic amount is disclosed after confirming the basic amount.
6. 낙찰자 결정 방법 ◐ 적격심사(추정가격이 고시금액 이상인 물품 구매입찰) ◐ 적격심사 평가기준 * 낙찰하한율: 80.495%(적격심사 통과점수: 85점 이상) {낙찰하한율은 입찰가격과 다른 심사분야의 배점한도(만점)를 합산한 경우 종합평점이 계약이행능력심사 통과점수에 해당하는 최저투찰률이오니 관련기준을 숙지하시고 입찰에 참여하시기 바랍니다}
B. Specific purchase details of the instant bid are as follows.
GHP (SUPER) GOC-1 large 1 GHP outside machine (SUPER) GOAC-2 large 4 GHP outside machine (SUPPER) GOC-3 large 11 EOAC-1 large 1.