(영문) 수원지방법원 성남지원 2017.11.17 2017고정1186
전기공사업법위반
Text

Defendant shall be punished by a fine of KRW 5,000,000.

When the defendant does not pay the above fine, 100,000 won.

Reasons

Punishment of the crime

The Defendant is an electrical construction business operator who runs the electrical construction business under the trade name, "E Co., Ltd." in Article 101 of the Jung-gu Seoul Special Metropolitan City D shop underground.

No constructor shall subcontract electrical construction works he/she has contracted to other constructors, and no constructor shall receive a subcontract therefor.

On February 2, 2015, the Defendant ordered “G contract amount: KRW 144,905,000 (G contract amount: KRW 144,905,00)” at a mutually infinite coffee shop in Seongbuk-gu, Sungnam-si, Sungnam-si, and received a subcontract from the said F.

Summary of Evidence

1. Partial statement of the defendant or F

1. One-time protocol concerning the examination of suspect of the police against the accused;

1. A protocol concerning the examination of suspect with respect to F;

1. Details of each account;

1. Response of the Labor Welfare Service;

1. The defendant and his defense counsel asserted that the defendant introduced human resources to H Co., Ltd. (hereinafter “H”) upon F’s request, and supplied materials, but the construction work as indicated in the judgment (hereinafter “the construction work in this case”) did not receive a subcontract from H.

However, the following circumstances acknowledged by the evidence duly adopted and investigated by this court, namely, F, the representative of H, who was awarded a contract for the instant construction work by the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office of the branch office

In addition to the materials worth KRW 15,994,00, other materials are not submitted by specifying the payment of labor cost, etc., and in addition to the wages paid to the above I who is the on-site representative, it is not submitted.